Erie Town Center's Grocery Deadline Applies to the Town, Too

The roughly 20-acre field at Erie Parkway and County Line Road looks empty from the road. There is more under it than on it. The Town of Erie bought the parcel in 2022 after an earlier development attempt by a different owner fell apart. It then picked Evergreen DevCo to build a town center with a grocery store at the front of the plan, as the Daily Camera reported in February 2025.

The site is undermined by the Garfield No. 1, Garfield No. 2 and Lister coal mines, worked from the late 1800s into the early 1900s. Because of those mines, the grocery store depends on a date now about eight weeks away, and the Town has as much riding on that date as the developer does.

The Contract Runs Out on New Year's Eve

In December 2025, the Town and its urban renewal authority, TOEURA, approved a restated development agreement with Evergreen for Phase 1 of Erie Town Center. That phase is planned to include a grocery store, restaurants, retail, public plazas, and the streets, sidewalks, utilities and stormwater work to support them.

The agreement calls the window the "Approvals Period" and sets it to end on December 31, 2026. Under the text of the agreement, three conditions have to be met by then:

  1. Evergreen has to secure a binding commitment from an anchor grocer, including "a commercially reasonable construction schedule indicating when the Anchor Grocer will open for business."
  2. Evergreen has to obtain all the entitlements for the development, including final plats, site plans, and construction and building permits.
  3. The Town has to finish the subsidence mitigation "at its sole cost and expense," get approval from the Colorado Geological Survey and any other required approvals, and assign the mitigation warranty to Evergreen.

Most of the attention goes to the first condition, because the grocer is the part residents would actually use. The third condition is the one that changes how to read the deadline. Evergreen can sign a grocer and still miss December 31 if the ground work under the site is not finished. That work belongs to the Town, and the Town pays for it.

Why the Ground Costs More Than the Store

The mines turned a straightforward retail project into a public financing project. Speaking to Town Council in February 2025, Evergreen CEO Tyler Carlson said the project "will not occur without a very significant public-private partnership on the financial side," according to the Daily Camera. He estimated $4 million to $5 million of grout pumped into the ground over about a year. In the same story, Mayor Andrew Moore described the town as "proposing to pump a lot of money into a hole underground that for the time being is not generating anything."

Ten months later, the restated deal attached firm numbers to that gap. According to the December 2025 staff presentation, the deal breaks down like this:

Commitment Who carries it Amount
Mine mitigation at Town Center Town of Erie, through Certificates of Participation $5.1 million
Project fund from tax increment and PIF revenue TOEURA Up to $15.7 million
Backup road funding if TOEURA's fund falls short Town's Transportation Impact Fund Up to $2.5 million
Land for Phase 1 Town conveys it to Evergreen No cost
Total public reimbursements Town and TOEURA combined Capped at $21.3 million

The $5.1 million for mitigation is more than Carlson's early grout estimate. It is also the one line in the table that has to be spent and finished before the Approvals Period ends. In January 2026, Town Council considered a $170,000 engineering services item with CTL Thompson. CTL Thompson would investigate the undermining, develop a final plan with the Town's mitigation contractor, and work with the Colorado Geological Survey on the development limits for the site. The staff background said the mitigation project was expected to "begin this spring."

What the Town's Own Updates Have Said This Year

The Town reports on Erie Town Center every month in its business newsletter. Read in order, the 2026 entries show where the project has stalled and where it has moved.

Newsletter Town Center status, in the Town's words
February 9 CTL Thompson contracted for more borings and a mitigation plan; construction bids expected to be published in March 2026
April 13 "Mine mitigation planning advances, site plan updates are in review, and negotiations with a potential grocer continue."
May 11 "Site plan submittal has been paused pending final grocer selection and site layout, mine mitigation planning has been completed"
June 8 Grocer recruitment and site coordination continue with Evergreen DevCo and Sullivan Hayes; "mine mitigation work is ongoing"
October 12 Grocer recruitment and site design continue, mine mitigation work is ongoing, and design is beginning for County Line Road improvements between Telleen Avenue and Erie Parkway

The May entry is the turning point. The Town finished its mitigation plan, and the site plan stopped moving because the grocer was not yet chosen, and the layout depended on the grocer. From June through the October newsletter, the wording has barely changed. No grocer has been named publicly. Without a grocer, the site plan and the permits that come after it cannot move forward either. The October update does add County Line Road design, a sign that public work around the edge of the site is still going ahead.

What the Contract Means by "Grocery Store"

Since 2025, the agreement has defined the anchor as "a smaller format, specialty grocer with not less than 8,000 square feet of building area and not more than 45,000 square feet." That definition sets expectations. The contract does not describe a full-line supermarket. It describes a smaller store, of the kind the Daily Camera called a "mid-size grocery center" when it reported on the early plans.

Several other terms shape what the shopping center would feel like once it opens:

  • Evergreen has to lease at least 30% of the leasable space, not counting the grocer, to food and beverage tenants, and is directed to give priority to local and regional businesses.
  • Once it owns the property, Evergreen is to put a 1% sales PIF and a 3% services PIF in place at the center, and that revenue is pledged toward paying for the project's public improvements. A PIF, or public improvement fee, is a charge added at the register. That means purchases there would carry a small extra charge on top of regular sales tax.
  • TOEURA's financing draws on new property-tax increment, 3.25 points of the Town's 3.5% sales tax generated inside the new urban renewal area, and the PIF receipts, according to the Town Council file on the restated agreement.

That last point connects the grocery store to the financing. The sales tax and fees collected at the center are what repay its public improvements, and that only starts once stores are open and making sales.

How the Contract Handles January

The agreement spells out what happens at the deadline. Before the Approvals Period ends, Evergreen has to send the Town and TOEURA written notice saying whether each of the three conditions has been met. If any has not, "the Town, TOEURA, or Developer may elect to terminate this Agreement by giving written notice to all Parties within 10 days." If Evergreen does not send the notice in time, it gives up its own right to terminate over those conditions.

The right to terminate is optional, so a missed condition does not automatically end the deal. Each side gets a 10-day window to decide whether to walk away. If the Town terminates before Evergreen starts construction, the agreement requires the Town to repay Evergreen $23,500 for its geotechnical investigation costs.

The date has slipped before. In February 2025, the Daily Camera reported that Evergreen needed a signed grocer letter of intent by mid-May 2025 to keep its place under the Town's RFP. The restated agreement that followed in December 2025 replaced the 2024 agreement and set December 31, 2026 as the date that now governs.

Between now and New Year's Eve, three public sources will show where things stand:

  • The November and December business newsletters. If a grocer is named, a site plan is submitted, or mitigation is finished, the Erie Town Center entry is the first place the change would show up.
  • Town Council and TOEURA agendas on Erie's Legistar portal. The restated agreement and the financing behind it were posted there when they were approved.
  • The site itself. Carlson's early estimate called for $4 million to $5 million of grout pumped into the ground over about a year, so finished mitigation would mean that work has happened on this field.

For background on how Erie's newer development pays for its public improvements, our post on the Erie number that isn't on the listing explains metro district levies. Our earlier look at why downtown Erie keeps changing on the same two streets covers the Town's other urban renewal projects. Neighborhood context is on the Erie neighborhood page.

This post is general information about a public agreement, not legal, tax or financial advice. Please confirm anything that affects your own plans with the right professional.

If you live near Erie Parkway and County Line Road and want to understand how the Town Center decision could affect your corner of Erie, I'm glad to talk it through and share updates as the Town posts them. Melissa Worth is always happy to connect.