Broomfield's Town Square Vote on December 8 Can Revoke the Plan. It Can't Hand the Land to Someone Else.

On December 8, Broomfield City Council is scheduled to decide whether to revoke the approved site plan for Broomfield Town Square. That's the 39-acre district planned north of West 120th Avenue and east of Main Street, meant to give the city a real downtown. The Land Use Review Commission recommended revocation after a hearing on October 26. Three days before that, the developer, Broomfield Town Square Alliance, sued the city for breach of contract.

A separate redevelopment agreement, signed in 2019, sits under the site plan, and the city's July 16, 2026 council presentation states that revoking the plan leaves that agreement in place. According to the Broomfield Enterprise, the agreement gives the developer team exclusive rights to build on the land until 2044. On December 8, Council decides whether the 2023 plan survives. If it doesn't, the developer decides what to submit next, and the land stays with the same partner.

The clock that ran out in September

According to the city's July presentation, Broomfield's municipal code gives every approved site development plan three years to reach vertical building permits for its primary structures. After that, the plan can be revoked. The presentation dates the Town Square plan's approval to September 12, 2023, which put the deadline at September 12, 2026.

At a Land Use Review Commission meeting, city staff explained that the three-year limit exists to make sure an approved plan still fits the community's needs years later, Denver7 reported. The city's July 16, 2026 council presentation made the same point more bluntly:

"The three-year SDP validity period, engineering review sequence, and permitting requirements are longstanding, consistently applied components of Broomfield's development process."

The same slide adds that they are not requirements unique to this project.

When Council voted unanimously in September to start the revocation process, Councilmember Julie Twiss brought the request on behalf of Ward 1, home of the planned Town Square, alongside Councilmember Katie Peterson. "We have received no substantive work product from the developers in over two months," Twiss said, according to the Broomfield Enterprise.

A start date that kept moving

The deadline didn't arrive as a surprise. The city's timeline shows the expected start sliding forward one step at a time:

  • August 2021: At concept review, construction on the Market Hall in the former Safeway building was expected to begin in late 2022 or early 2023.
  • May 2023: Construction and opening of Phase 1, including the Market Hall, moved to 2025. The developer reconfirmed that timeline in April 2024.
  • February and March 2025: Citing financial markets and trouble closing the equity stack, the target groundbreaking became August or September 2026.
  • February 2026: The developer's extension letter expected bond financing and groundbreaking in the second half of 2026. One of the bond scenarios filed with the same request put bond financing in March 2027, groundbreaking in 2027 and vertical permit submittals in early 2028. The developer verbally confirmed that second scenario as its current timeline at the April 21, 2026 study session.

The last date matters most. Early 2028 for vertical permits lands well after the September 2026 deadline, which is why the developer asked on February 18 for an 18-month extension to March 2028. On May 4 it added a second request: extend the city's financial participation from 2044 to 2050, a request the presentation describes as about $14 million in additional city commitment. On June 24 the developer withdrew both requests, saying it was "recalibrating and evaluating alternative paths forward for the project under the terms of the existing agreements."

What got filed, and what the deadline counted

The two sides disagree about what got done before September. According to Denver7, the developers say they applied for permits in March covering $30 million in improvements to the nearby swim beach, plaza, streets, sidewalks and trails, plus building permits for a boathouse and restrooms. Their lawsuit claims the city told them those permits weren't enough and that they had to show progress on the main buildings, and that the uncertainty stalled their financing.

The city's July presentation laid out the same filings this way:

Permit applications as of July 2026 Status
Infrastructure plans Submitted, under engineering review
Boathouse and restroom building, filed March 27, 2026 Reviewed, but can't be issued until grading and utility permits are issued
Residential buildings Not submitted
Mixed-use buildings Not submitted
Former Safeway redevelopment Not submitted

The presentation calls the boathouse and restrooms "accessory structures, not primary uses." It describes the buildings that hadn't been submitted as "the uses that define the project." Its takeaway was that vertical permits can't be issued until the engineering and horizontal infrastructure plans are approved, and that applications alone don't meet that milestone.

The lake raised a separate engineering question. The lake design report filed with the construction plans appeared to cut the lake's maximum depth from 12 feet to 8 feet and its average depth from 8 feet to 6. Staff warned that a change that size could affect water quality, circulation, temperature and the likelihood of algae blooms, as well as long-term maintenance, and asked whether it was intentional. According to Denver7, city leaders have since raised concerns that the developers didn't respond to that question.

The agreement under the plan runs to 2044

The site plan is the design. The 2019 Redevelopment and Reimbursement Agreement is the business deal, and that's where the money and the land come from. The city's July presentation lists a city land contribution valued at about $20 million and up to $54 million in tax increment financing available through 2044, $74 million in all, approved by the city and the Broomfield Urban Renewal Authority in 2019.

The presentation also says what happens if Council votes yes: "If the SDP is revoked, the 2019 Agreement remains in place and a new SDP will need to be submitted." City Attorney Nancy Rodgers told Council the developer team would then decide what comes next, which could mean resubmitting the same plan or submitting a new one, the Broomfield Enterprise reported. That's possible because the agreement gives the developer team exclusive rights to the land north of 120th Avenue and east of Main Street until 2044.

The developer is Broomfield Town Square Alliance. Council information identifies Outpost Partners and City Street Investors as the companies involved. The city's Town Square project page says potential revocation of the site plan is separate from the 2019 agreement, and that the city remains in compliance with that agreement.

So after a yes vote on December 8, the land doesn't go back on the market. The same partners hold it, under the same financial framework, and any new plan goes through public review again.

What a new plan would be measured against

The approved 2023 plan is the yardstick for anything that replaces it. Its first phase called for about 471 apartments and 12 townhomes, roughly 63,590 square feet of commercial space including the Market Hall in the long-vacant Safeway, and income-aligned housing. The lakeside program included an enlarged lake, trails, a plaza, a beach, a future boathouse, and lakeside restaurants and gathering areas, with room set aside for a possible Library and Auditorium expansion. The development has been described as a $300 million project.

The financing went beyond the city's contribution. The July presentation lists:

  • Two metropolitan districts levying 50 mills and 27.41 mills on top of the city's 28.96, paid by the project's commercial and residential tenants
  • A business improvement district at 15 mills, paid by commercial tenants
  • A 2% public improvement fee added to the current 8.15% sales tax, for 10.15% paid by shoppers inside the district
  • Private equity, bond financing and other private capital

If you've ever wondered why property tax bills vary across Broomfield, this is the same district-by-district pattern covered in our look at Broomfield's overlapping tax areas.

Nothing on the list changes the civic campus next door. The city's parks plan places the Broomfield Community Center, the George Di Ciero City and County Building, the Library and Auditorium, the Amphitheater, and the Police and Courts Building within Broomfield Community Park, along with The Bay Aquatic Park, trails, tennis courts, ball fields and playgrounds. The Town Square dispute is about the parcel beside them.

December 8, with a lawsuit running alongside

The steps so far: Council approved a notice on October 13 requiring the developer to show why the plan should stay in place. The developer filed suit on October 23. The Land Use Review Commission held its hearing on October 26 and recommended revocation, a recommendation that isn't final. The Longmont Leader describes the December 8 decision and the contract lawsuit as separate questions, each waiting on further action.

Council members have said they still want the project built. "Council has been unified in that we all want Broomfield to have a town square and we know our community does too," Twiss said, according to the Broomfield Enterprise. "But wanting that vision cannot mean that we stop expecting progress, performance and accountability." A resident who lives near the site told Denver7 it's within walking distance of his home and would be a nice place to "go get coffee, ice cream, a beer after work," and asked the city for "a little grace" and an extension if the developer is still interested.

Both of those views assume the same partner either way. Under the 2019 agreement, the coffee, the Market Hall and the lakeside plaza all depend on Broomfield Town Square Alliance moving forward, with this plan or a new one. The city's Town Square page is where the city posts updates on the project.

If you live near 120th and Main and want to talk through what the Town Square timeline could mean for your own plans, whether you're staying put, selling or buying nearby, I'm happy to walk through it with you. Let's connect at Melissa Worth, or start with the Broomfield neighborhood guide.

Real Estate That Grows with Your Life

Every stage of life brings new opportunities and new housing needs. From first homes and growing families to retirement, relocation, and everything in between, I provide the guidance, local knowledge, and education you need to make confident decisions while building the future you envision.

Follow Me on Instagram